Enter Planned Value, Earned Value and Actual Cost for each task, and let the formulas do the rest. All ten EVM metrics auto-calculate: Schedule Variance, Cost Variance, SPI, CPI, EAC, ETC, VAC and more. A summary metrics panel at the top gives you the project-level picture in seconds.
No email required. Instant Excel download.
All 10 EVM Metrics: Formulas and Meaning
The template auto-calculates all ten standard EVM metrics from three inputs. The three blue cards below are the inputs you enter. Everything else is calculated automatically.
How to Interpret CPI and SPI Values
The two performance indices, CPI and SPI, are the numbers sponsors ask for most. Both use the same logic: above 1.0 is good, below 1.0 is a concern, exactly 1.0 is on plan.
| Value | Meaning | CPI Interpretation | SPI Interpretation | Action |
|---|---|---|---|---|
| > 1.0 | Favourable | Under budget: getting more value than spent | Ahead of schedule: completing work faster than planned | Monitor. Investigate if significantly above 1.2: may signal under-reporting of AC or incorrect EV. |
| = 1.0 | On Plan | Exactly on budget | Exactly on schedule | Continue. No intervention needed. |
| 0.9–1.0 | Watch | Slightly over budget: early warning | Slightly behind schedule | Investigate root cause. No escalation yet but monitor closely each period. |
| 0.8–0.9 | Concern | Meaningfully over budget: recovery needed | Meaningfully behind schedule | Formal corrective action plan. Sponsor notification. Review EAC and ETC. |
| < 0.8 | Critical | Severe cost overrun: project viability at risk | Severely behind schedule | Escalate immediately. Consider re-baselining. Project may need formal recovery or scope reduction. |
Worked Example: Reading a Project's EVM Snapshot
Reading this snapshot: the project has completed work worth $153K of its planned $180K schedule. It is 15% behind on schedule. It has spent $175K to achieve that $153K of value, so it is also running 13% over cost. If CPI of 0.87 continues, the EAC = BAC ÷ 0.87. On a $540K project that means a forecast final cost of ~$621K, a $81K overrun. This is the power of EVM: you can forecast the final outcome in Month 4 of a 12-month project.