Free Budget Variance Report Template
Excel Download
Compare planned vs actual costs across every work package on your project. Auto-calculates variance in dollars and percentage, totals the whole project automatically and gives you a clear RAG status column to flag cost overruns before they escalate.
No email required. Instant Excel download.
What's in the Template
The Budget Variance Report is a single-sheet Excel file with a branded header, project metadata block, 12 pre-labelled work package rows and a violet auto-summing totals row. The Variance ($) and Variance (%) columns are live formulas — enter your budget and actual figures and everything else calculates instantly.
| Column | Field | Notes |
|---|---|---|
| WP ID | Work Package ID | Pre-filled WP-01 through WP-12. Customise to match your WBS numbering. |
| Work Package | Category Name | Pre-labelled: Labour (PM, Dev, Design, Test), Hardware, Software, Cloud, Travel, Training, Contingency, Management Reserve, Other. |
| Budget ($) | Planned Cost | Enter the approved budget for this work package. Formatted as currency. |
| Actual ($) | Actual Spend | Enter the actual cost incurred to date or for the period. Formatted as currency. |
| Variance ($) | Formula | Auto-calculated: Budget minus Actual. Positive = under budget. Negative = over budget. Shown in red brackets if negative. |
| Variance % | Formula | Auto-calculated: Variance ÷ Budget. Shows percentage over or under. Positive = under, negative = over. |
| Status | RAG Indicator | Enter 🟢 Green / 🟡 Amber / 🔴 Red manually based on your threshold rules. |
| Notes | Explanation | Free text. Explain the cause of any significant variance — essential for sponsor reports. |
The Totals Row
The violet totals row at the bottom auto-sums the Budget, Actual and Variance ($) columns across all 12 work packages. The total Variance % is also calculated automatically as (Total Budget − Total Actual) ÷ Total Budget. This gives you the overall project cost position at a glance without any manual addition.
Budget Variance Formulas — Explained
The template uses two core formulas. Both are live — update the Budget or Actual figures and variance columns recalculate immediately.
Reading a Variance — Worked Example
How to Use the Budget Variance Report
Setting RAG Thresholds for Budget Variance
The RAG (Red, Amber, Green) status column requires you to define thresholds — the percentage variance that triggers each colour. Common industry standards are:
| RAG Status | Typical Threshold | What it Signals | Action Required |
|---|---|---|---|
| 🟢 Green | Within ±5% of budget | On track — normal variation | Monitor. No action needed unless trend is worsening. |
| 🟡 Amber | 5–15% over budget | At risk — approaching concern | Investigate cause. Identify corrective action. Inform PM and sponsor. |
| 🔴 Red | >15% over budget | Off track — action required | Escalate to sponsor. Raise change request if scope is driving cost. Formal recovery plan required. |
These thresholds vary by organisation. Some use tighter bands (±3% / 3–8% / over 8%) for high-scrutiny projects. Agree your specific thresholds with the sponsor and finance team before the project starts and document them in your project status report.
Under Budget Isn't Always Good
A large positive variance (significantly under budget) can signal that planned work has not been done — not that the project is being delivered efficiently. If you're 20% under budget at the midpoint, check whether the project is also ahead of schedule. If it is, great. If it isn't, the under-spend may reflect delayed or missed work packages that will create a cost spike later.