Free EVM Tracker Template
Excel Download
Enter Planned Value, Earned Value and Actual Cost for each task — and let the formulas do the rest. All ten EVM metrics auto-calculate: Schedule Variance, Cost Variance, SPI, CPI, EAC, ETC, VAC and more. A summary metrics panel at the top gives you the project-level picture in seconds.
No email required. Instant Excel download.
All 10 EVM Metrics — Formulas and Meaning
The template auto-calculates all ten standard EVM metrics from three inputs. The three blue cards below are the inputs you enter — everything else is calculated automatically.
How to Interpret CPI and SPI Values
The two performance indices — CPI and SPI — are the numbers sponsors ask for most. Both use the same logic: above 1.0 is good, below 1.0 is a concern, exactly 1.0 is on plan.
| Value | Meaning | CPI Interpretation | SPI Interpretation | Action |
|---|---|---|---|---|
| > 1.0 | Favourable | Under budget — getting more value than spent | Ahead of schedule — completing work faster than planned | Monitor. Investigate if significantly above 1.2 — may signal under-reporting of AC or incorrect EV. |
| = 1.0 | On Plan | Exactly on budget | Exactly on schedule | Continue. No intervention needed. |
| 0.9–1.0 | Watch | Slightly over budget — early warning | Slightly behind schedule | Investigate root cause. No escalation yet but monitor closely each period. |
| 0.8–0.9 | Concern | Meaningfully over budget — recovery needed | Meaningfully behind schedule | Formal corrective action plan. Sponsor notification. Review EAC and ETC. |
| < 0.8 | Critical | Severe cost overrun — project viability at risk | Severely behind schedule | Escalate immediately. Consider re-baselining. Project may need formal recovery or scope reduction. |
Worked Example — Reading a Project's EVM Snapshot
Reading this snapshot: the project has completed work worth $153K of its planned $180K schedule — it is 15% behind on schedule. It has spent $175K to achieve that $153K of value — so it is also running 13% over cost. If CPI of 0.87 continues, the EAC = BAC ÷ 0.87. On a $540K project that means a forecast final cost of ~$621K — a $81K overrun. This is the power of EVM: you can forecast the final outcome in Month 4 of a 12-month project.