Certifications PMP CertificationWorld’s top PM cert CSM: Certified ScrumMasterTop agile cert CAPMEntry-level PM cert PRINCE2UK & Europe standard View All Certifications ?
PM Guides Agile GuideComplete breakdown Scrum GuideRoles, ceremonies, artifacts EVM GuideAll formulas explained View All Guides ?
Career & Salary PM Salary 2026By country & level How to Become a PMStep-by-step roadmap 50 Interview QuestionsWith strong answers
PM Software Monday.com ReviewTop pick 2026 ClickUp ReviewBest value Best Free PM ToolsNo trials, truly free View All Software ?
Free Tools & Templates EVM CalculatorFree, no signup Gantt Chart MakerBuild & export free PMP Eligibility Checker30-second result Free PM Templates30 templates in Excel, Word and PDF
Get the Free PMP Guide ?
Free Template · Updated March 2026

Free Risk Register Template
Excel, Sheets & PDF

I built this risk register on how I actually managed risk on construction projects in the UAE, including multi-million projects. It has 15 example risks across 8 categories, automatic colour-coded scoring, a 5x5 heat map, drop-downs and residual risk tracking. Download it free in Excel and open it in Google Sheets in one click.

✓By Syed Mujeeb Ur Rehman, PMP
✓Updated March 2026
✓3 sheets · 15 example risks
✓Free: no signup
What's Inside

Three sheets: Risk Register (15 pre-filled risks, auto-scoring, dropdowns), Risk Matrix (5x5 heat map with risks plotted), and Instructions (step-by-step guide). Scores calculate automatically. RAG colours update instantly. Fully editable.

1–4
Low
5–9
Medium
10–16
High
17–25
Critical

Risk score = Probability (1–5) × Impact (1–5): colour updates automatically

Download Free Template

Excel (.xlsx) · Works in Google Sheets too

RISK REGISTER
R-001 · Scope Risk · CRITICAL
R-002 · Resource Risk · HIGH
R-003 · Vendor Risk · MEDIUM
R-004 · Scope Risk · LOW
+ 11 more pre-filled risks…
.XLSX Google Sheets FREE
  • 15 pre-filled risks across 8 categories
  • Auto-scoring: Prob × Impact = Score
  • RAG colours update automatically
  • 5x5 probability-impact heat map
  • Dropdown validation on all key fields
  • Residual risk tracking (post-response)
  • Risk count summary row
  • 30 blank rows for your own risks
  • Step-by-step instructions sheet
↓ Download Free (.xlsx) Open in Google Sheets →
15
Pre-filled example risks included
3
Sheets: Register, Heat Map, Instructions
4
Auto-colour bands: Low to Critical
Free
No account or payment required

Quick answer

A risk register is a log of every identified project risk with its probability, impact, owner and planned response. This free Excel template has 3 sheets, 15 pre-filled example risks across 8 categories and automatic risk scoring, so you can see which risks need action first.

If you want to learn the full risk process, from finding risks to choosing responses, read my risk management guide. This page is for the template itself: how to fill it in row by row, with a worked example.

Risk Register template preview: 15 example risks in 8 categories, Probability x impact scoring, Owner and response per risk, 3 sheets, ready to edit
What is inside the free risk register template.
01 · Template Contents

What's inside the risk register template?

Every column in this register has a reason. I did not add anything that does not earn its place on a real project. Here is exactly what each column captures and why it matters.

From my experience: On my UAE construction projects, the risks that hurt us were rarely surprises. Late consultant approvals, long-lead equipment, failed authority inspections: we knew they could happen. The problem was when nobody owned them. A risk with a named owner and a dated action got managed. A risk owned by "the team" just sat in the register. When I teach this to my PMP students, I ask them to check one column first: Owner.
ColumnWhat It CapturesNotes
IDUnique risk identifier (R-001, R-002…)Pre-filled. Use it to cross-reference risks in status reports and steering committee packs.
CategoryRisk type: Scope, Resource, Schedule, Budget, Quality, Technical, Stakeholder, ExternalDropdown menu. Select from 10 categories.
Risk DescriptionClear statement of the risk event and its potential impactWrite as "If [event], then [consequence]." This format forces clarity.
Risk OwnerPerson accountable for executing the response planDo not default every risk to the PM. Ownership must match expertise.
Probability (1–5)Likelihood of the risk occurringDropdown: 1=Rare, 2=Unlikely, 3=Possible, 4=Likely, 5=Almost Certain
Impact (1–5)Severity if the risk materialisesDropdown: 1=Negligible to 5=Catastrophic
Risk ScoreProbability × Impact: auto-calculatedColour updates automatically: Green, Yellow, Orange, Red
RatingLow / Medium / High / CriticalAuto-colours based on score threshold
Response StrategyAvoid / Mitigate / Transfer / Accept / EscalateDropdown menu
Response ActionSpecific steps to execute the responseName who does what and by when. Vague actions get ignored.
Contingency PlanWhat to do if the risk materialises despite the responsePlan this in advance. Do not improvise under pressure on a live project.
Residual ProbProbability after response actions are in placeShould be lower than original probability if the response is effective.
Residual ImpactImpact after response actions are in placeSome risks can only reduce probability, not impact. Know the difference.
Residual ScoreResidual Prob × Residual Impact: auto-calculatedShows remaining risk exposure after mitigation. This is your true risk position.
StatusOpen / In Progress / Closed / CancelledDropdown. Open risks are highlighted in violet so nothing gets missed.
02 · Risk Scoring

How does risk scoring work?

The score works out automatically as Probability × Impact. Both use a 1 to 5 scale, so the score runs from 1 to 25. The colour changes the moment you change either number. No formulas to set up and no manual colouring.

Probability Scale (Column E)

1 · Rare: Less than 10% chance. Theoretically possible but very unlikely. 2 · Unlikely: 10 to 30% chance. Has happened on similar projects but not expected here. 3 · Possible: 30 to 60% chance. Could easily go either way. Flag every Possible risk for active attention. 4 · Likely: 60 to 80% chance. Expected to happen unless you actively manage it. 5 · Almost Certain: More than 80% chance. At this point you are dealing with an issue, not just a risk.

Impact Scale (Column F)

1 · Negligible: Minor disruption, easily absorbed within normal project operations. 2 · Minor: Small schedule or cost impact manageable within existing contingency. 3 · Moderate: Noticeable impact on one or more project constraints. Sponsor needs to be aware. 4 · Major: Significant impact on schedule, budget or scope requiring formal change control. 5 · Catastrophic: Project failure, major financial loss, reputational damage or regulatory breach. On my UAE projects, anything at Impact 5 went straight to the steering committee.

✦
PMP exam tip and real project advice: The residual score after your response matters as much as the first score. If your response takes a Critical risk from 20 down to 12, that is progress, but 12 is still High. Some risks stay above your comfort level whatever you do. For those, you still need a contingency plan. I have seen teams think a risk is handled just because a response was written down. The residual score tells you the truth.
Worked example

How to fill in the risk register: a worked example

Here are three rows filled in the way I would on a building project in the UAE. This is an example only, not data from a real project. Look at how each description follows "If..., then..." and how the residual score shows what is left after the response.

IDRisk descriptionP x I = ScoreResponse and ownerResidual
R-001If consultant approval of the facade shop drawings is late, then fabrication cannot start and the facade handover slips.4 x 4 = 16 (High)Mitigate. Submit early, track in a weekly submittal log, book review meetings. Owner: design manager.2 x 4 = 8 (Medium)
R-002If the chillers ordered from overseas arrive late, then MEP testing and handover slip.3 x 5 = 15 (High)Mitigate. Order early, track shipping weekly, agree a temporary cooling option as contingency. Owner: procurement manager.2 x 5 = 10 (High)
R-003If the Civil Defence inspection fails, then the completion certificate is delayed.3 x 4 = 12 (High)Mitigate. Pre-inspection walk with the MEP consultant two weeks before. Owner: MEP coordinator.2 x 4 = 8 (Medium)

See R-002: the response lowers probability but not impact. That is why it stays High and still needs a contingency plan.

Mistakes I see when people fill this in

  • Known facts logged as risks. The summer midday work break is not a risk. It will happen. Plan for it in the schedule.
  • Causes instead of risks. "Shortage of labour" is a cause. Write what might happen because of it and what it will hit.
  • Every risk owned by the PM. Give each risk to the person best placed to act on it.
  • Residual columns left blank. Without them, you cannot show whether your responses are working.
  • Risks that happened left as risks. Once it has happened, move it to the issue log.
03 · Response Strategies

What are the five risk response strategies?

Picking the right response is one of the biggest calls you make as a PM. I have seen experienced PMs pick Mitigate for every risk out of habit. Here is when each strategy really fits.

Avoid
Change the project plan to eliminate the risk entirely. Remove the risky activity, change the approach or scope it out completely.
Best for: High-probability, high-impact risks where a viable alternative approach exists.
Mitigate
Reduce the probability of the risk occurring, reduce the impact if it does, or both. The most commonly used strategy and the right one when you cannot avoid the risk.
Best for: Risks you cannot avoid but can reduce through proactive, planned action.
Transfer
Shift the financial consequence to a third party through insurance, warranty clauses, fixed-price contracts or outsourcing. Transfer does not eliminate the risk. It moves who bears the cost.
Best for: Financial or technical risks where a vendor or insurer is better placed to absorb the impact.
Accept
Acknowledge the risk and decide not to act unless it materialises. Active acceptance means you prepare a contingency plan. Passive acceptance means you do nothing and deal with it if it happens.
Best for: Low-scoring risks where the cost of responding exceeds the cost of the risk itself.
Escalate
Raise the risk to the programme manager, sponsor or organisational level because it is beyond the project manager's authority or scope to manage alone. Always document the escalation. Record who it was raised to and when. On my UAE projects, regulatory risks and major supplier risks went straight to the client and steering committee. The PM should never sit on a risk that is above their authority level.
Best for: Risks affecting multiple programmes, requiring executive decisions or needing an organisational-level response.
04 · FAQ

Risk Register: 5 Common Questions Answered

A risk register is the one place where you record every risk you have found on the project, with its probability, impact, response, owner and status. In PMBOK 6 it is first created in the Identify Risks process, and you keep updating it until the project closes. I used one on every project I managed in the UAE. Review it with your team weekly and at every steering meeting. A register that is never updated is worse than none, because it makes people feel safe when they are not.
A complete risk register needs: unique risk ID, risk category, clear risk description, risk owner, probability score (1 to 5), impact score (1 to 5), overall risk score (probability × impact), risk rating (Low, Medium, High or Critical), response strategy, specific response actions, contingency plan, residual probability and impact after responses are applied, and current status. This template includes all 15 fields. Everything I just listed is in there.
Risk score = Probability × Impact. Both are rated 1 to 5. Probability: 1=Rare (less than 10%), 2=Unlikely (10 to 30%), 3=Possible (30 to 60%), 4=Likely (60 to 80%), 5=Almost Certain (more than 80%). Impact: 1=Negligible, 2=Minor, 3=Moderate, 4=Major, 5=Catastrophic. The score maps to: 1 to 4 Low (green), 5 to 9 Medium (yellow), 10 to 16 High (orange), 17 to 25 Critical (red). This template calculates and colours the score automatically. You just enter the two numbers and everything else updates.
For threats, PMI lists five strategies: Escalate (the risk is outside your authority, so you pass it up), Avoid (change the plan to remove it), Transfer (move it to a third party through insurance or a contract), Mitigate (reduce probability or impact) and Accept (watch it, with or without a contingency plan). For opportunities the five are Escalate, Exploit, Share, Enhance and Accept. My risk management guide explains each one with examples.
Review the full register at every steering meeting, often every two weeks. Risk owners should update their own risks every week. At each phase gate, check every score and response again. New risks can appear at any time, so I ran a short risk session at the start of every new phase. Never delete closed risks. Mark them Closed and keep them. They are your audit trail and they feed your lessons learned at closeout.